CBS Codes
You can create and update the CBS Codes in Unifier Cost Sheet via Primavera Gateway integration with any Oracle application.
In Primavera Gateway, you can run the Create CBS in Unifier Cost Sheet synchronization to send WBS structures and codes from P6 schedules to Unifier as CBS codes for cost sheets.
WBS codes imported from P6 through Primavera Gateway as CBS cost codes into Unifier cost sheets adhere to the following rules:
- Imported CBS codes reside within their own imported hierarchical structure. They get appended to the existing CBS hierarchy in the destination cost sheet.
- Imported CBS codes maintain the same sequence as the WBS codes specified in the P6 schedule. The sequence must be maintained even when you manually add CBS codes.
- CBS codes are created with an Active status.
- CBS codes created through P6 integration or CBS Codes with transactions cannot be edited.
- A CBS code is considered duplicate only if they appear at the same level. Therefore, a parent code cannot contain duplicate child codes.
- CBS codes cannot contain the character identical to the cost code separator.
- If the number of Unifier cost sheet segments is greater than the number of WBS levels in P6, then the following Unifier CBS codes are created for each lowest level WBS sent from P6:
- A summary CBS code
- A leaf CBS code below the summary CBS code
However, you can manually create additional hierarchical nodes below the imported structure.
For example, when a four-segment WBS hierarchy in P6 is imported into a five-segment CBS cost codes hierarchy in Unifier:
P6 WBS Code | Unifier CBS Code | Comments |
---|---|---|
1 | +1.0.0.0.0 |
|
1 | +1.1.0.0.0 |
|
1 | +1.1.1.0.0 |
|
1 | +1.1.1.1.0 |
|
| +1.1.1.1.0 | This CBS code is created for the lowest-level WBS code imported from P6 |
2 |
|
|