Project or Shell Cost Sheet
When you open a project/shell cost sheet, the Cost Sheet overlay window opens and the following elements appear on the screen:
- Cost Sheet header and locked/unlocked indicator
- Toolbar enabling access to several actions
- Grid with rows (if available) and columns
To open a cost sheet:
- Go to the shell tab and switch to User mode.
- In the left Navigator, select Cost Manager, and the select Cost Sheet.
- In the Cost Sheet log, open the applicable cost sheet.
The Cost Sheet overlay window toolbar options are as follows:
Option | Description |
---|---|
Manage Rows | Note: This option is available only to those users who have permission to modify the cost sheet rows. Clicking this option enables you to open a new grid sheet (inline), on top of the cost sheet, titled: Manage Rows. For a tree-structure cost sheets, the Manage Rows sheet has the following toolbar options:
Note: When no cost code has been created yet, the toolbar has only the Add option (instead of the two separate Add Sibling and Add Child options).
For a flat-structure cost sheets, the Manage Rows sheet has the following toolbar options:
When you make changes, the following additional options (upper-right corner of the screen) enable you to cancel or save your changes:
The Manage Rows sheet has the following columns that are stationary:
Other columns on the Manage Rows sheet vary as per design (as defined in the Cost Sheet Attribute Form in uDesigner). For each cost code row in the Manage Rows sheet, you have the following options columns at the very end:
Note: When a record is terminated or a rolled up line item is deleted, the system still maintains references to these line items with the CBS code. In such scenarios, the referenced CBS codes cannot be deleted. However, if a CBS code is referenced by a line item data either by direct cell entry or a manual line item is created in the cost sheet, upon deleting the line item data from the cost sheet, you can delete the CBS codes.
For each cost code row in the Manage Rows sheet, there is a right pane (bottom) that captures more details on the code. This pane contains following tabs:
For a tree-structure cost sheet, the right-click options for a cost code row, within Manage Rows window, are:
For a flat-structure cost sheet, the right-click options for a cost code row, within Manage Rows window, are:
For both a tree-structure cost sheet and a flat-structure cost sheet, when you select multiple rows, the right-click options are:
|
Add Column | Enables you to open the New Column overlay window which contains the following fields:
Note: The data sources that have been used to create a column will not be included in the list. To create the column successfully, you must populate the required options on the form.
Note: In Cash Flow, Cost Sheet, and Earned Value, you can replace the Summary Sheet with the Activity Sheet as a source.
The New Column overlay window has the following action options:
|
View | These options let you use a default view, create your own views, and manage (rearrange, hide, show, and delete) views. For more information, see Cost Sheet Views.
|
Edit View | Use this option to modify the current view. |
Forecasting | Note: This option is available only if the cost sheet is enabled for forecasting. When you click this option, the Classic View of Forecast Adjustment window opens. |
Refresh | Enables you to see the added values to the columns of the sheet. |
Print | Use this option to print or export the log content. |
Find on Page | Use this option to search for specific entries in the sheet. |
Expand All Groups | Enables you to expand or collapse the sheets to see the subordinates. |
Menu Options | Enables you to conduct and access:
|
Currency Toggle | Enables you to switch the cost sheet currency from Project Currency to Base Currency (or conversely). |
The Cost Sheet overlay window column options may vary. The following are a list of possible columns:
- Sequence No.
- CBS Code (or Cost Code): Static column
- CBS Item (or Code Name): Static column
- Assigned Budget
- Purchase Orders (Approved)
- Change Orders (Approved)
- Invoices (Approved)
- Contingencies
- LI Content
- Risks & Issues (Closed)
- Forecasts
- Budget Approval (Approved)
- Budget Transfers (Approved)
- CBS/WBS Actuals (Approved)
- Contract Change Orders (Approved)
- Contracts (Approved)
The bottom of the Cost Sheet log (underneath the second column from the left, after the Sequence No. column) displays the totals for the amounts for each column.
The lower-left corner of the Cost Sheet log displays the total number of items.
When you right-click a cell heading, you will see the following options:
- Insert
- Properties
- Hide
- Delete
- Lock after this column
When you right-click a cell within the cost sheet, you will see the following options:
- Add Sibling Row
- Add Child Row (available only if the selected cell row is not associated with any cost item or line item data)
- Insert Column Before (not available if you select a cell within the CBS Code or the CBS Item columns)
- Insert Column After (not available if you select a cell within the CBS Code or the CBS Item columns)
- Copy
- Delete
When you click a cell, the Cost Sheet screen opens a pane on the right side that has the following tabs:
- General
- Attachments
- Notes
- Fund Assignment Order
These tabs provide additional information about each cell. Where allowable, you can update the fields within each tab.
The Budget Distribution overlay window contains the following elements:
Element | Description |
---|---|
When the Budget Distribution is locked (padlock icon in locked position) | The following blocks (accordion menu) are visible:
If you click Unlock, you must enter a reason. |
When the Budget Distribution is unlocked (padlock icon in unlocked position) | You have all the options available in the locked position, and you can change the values in the editable fields. Once finished, you must click Save & Lock. |