Adding Portfolio Budget Curve for Cash Flow by Summary CBS or CBS
Summary CBS
To add Portfolio Budget (Approved Budget) curve for cash flow by Summary CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select Summary CBS.
- In the Curves pane, select Approved Budget.
The Approved Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Original Budget) curve for cash flow by Summary CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select Summary CBS.
- In the Curves pane, select Original Budget.
The Original Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Shared Budget) curve for cash flow by Summary CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select Summary CBS.
- In the Curves pane, select Shared Budget.
The Shared Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
CBS
To add Portfolio Budget (Approved Budget) curve for cash flow by CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select CBS.
- In the Curves pane, select Approved Budget.
The Approved Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Original Budget) curve for cash flow by CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select CBS.
- In the Curves pane, select Original Budget.
The Original Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Shared Budget) curve for cash flow by CBS:
- Select the cash flow from the Cash Flow log.
- Select the gear menu (
), and select the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet). - In the General pane, select CBS.
- In the Curves pane, select Shared Budget.
The Shared Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Parameter | Description |
|---|---|
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
Currency | Select to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |