Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.

To assign a resource curve:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Display the Curves column if it is not visible on the table. To display the Curves column, click  Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
    2. On the Assignments page:
      • Click the row with the resource or role.
      • Double-click the Curve field, and click Select .
    3. In the Select Curves dialog box, choose a curve and click OK.
    4. On the Assignments page, click Save.

Tip

You can also assign resource curves to resource or role assignment from the Activities page.

Related Topics

Defining Resources and Roles

About Roles

Creating Roles

Assigning a Resource to a Role

Assigning a Role Team to a Role

About Role Teams

Creating Role Teams

Assigning a Role to a Role Team

About Resources

Adding Resources

Assigning a Role to a Resource

Assigning a Resource Team to a Resource

Configuring Resource Settings

Assigning Calendars to Resources

Configuring Timesheet Reporting for Resources

Assigning Resource Codes

Assigning Resource Rates

Assigning Role Codes

About Resource Teams

Creating Resource Teams

Assigning a Resource to a Resource Team

Assigning Resource Curves to Resource or Role Assignments from the Activities Page



Last Published Monday, October 13, 2025