Selecting an Activity for Review

Select an activity for review to enable the project manager or assigned status reviewers to approve the activity when updated by a team member before the status updates are applied to the project.

To select an activity for review:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Select the Review Required option.

      Note If the Review Required option is not displayed, click  Customize View and select the Columns tab, then select Review Required from the General category.

    3. Save your changes.

Tip

Related Topics

About P6 Team Member Status Updates

Working with P6 Team Member Status Updates

Assigning a Status Reviewer to a WBS

Reviewing Team Member Status Updates

Viewing Team Member Status Updates History

Configuring P6 Team Member Status Update Reviews