Configuring Gantt Charts

On the EPS and Activities pages, configure the Gantt chart to adjust activity beginning and finishing dates as well as constraints.

To configure the Gantt chart:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities or EPS.
  3. On the Activities or EPS page, click Gantt View.
  4. On the Gantt chart:
    1. To resize bars, select a bar and click and drag the beginning or end of it to a new date. (Only applicable on the Activities page.)
    2. To expand a specific area of the Gantt chart, hover over the timescale at the top of the Gantt chart (the pointer will become a double-headed arrow), move the pointer to select the portion of the timescale you want to expand, and click again. You can perform this step several times.
    3. To apply a Start On or After Activity Constraint, click the middle of a bar and drag it along the timescale. (Only applicable on the Activities page.)
  5. On the Activities or EPS page, click Save.

Tip:

Related Topics

About Gantt Charts

Working with the Activity Gantt Chart

Configuring Activity View Gantt Chart

Creating Activity Relationships

Configuring Activity Relationships