Creating Activity Issues

Create activity issues to identify problems that must be addressed before a project can be completed.

To create activity issues:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity and click the Issues detail window.

    Note To create a project or WBS issue, select a project or WBS in place of an activity.

  4. In the Issues detail window:
    1. Click  Add.
    2. Enter or select a value for the Issue Name, Priority, Status, and Responsible Manager fields.
  5. On the Activities page, click Save.