Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.

To assign a resource curve:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Display the Curves column if it is not visible on the table. To display the Curves column, click  Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
    2. On the Assignments page:
      • Click the row with the resource or role.
      • Double-click the Curve field, and click Select .
    3. In the Select Curves dialog box, choose a curve and click OK.
    4. On the Assignments page, click Save.

Tip

You can also assign resource curves to resource or role assignment from the Activities page.

Related Topics

Resource Assignments

About Resource Assignments

About Assignments Views

Working with Resource Assignments in the Gantt Chart

Viewing Assignment Unit and Cost Spreads

Assigning a Resource to an Activity Assignment

About Future Period Planning

Assigning Resource Curves to Resource or Role Assignments from the Activities Page