Leveling Results Section of the Leveling Report Log

Overview

Use this section to view the results of leveling for the selected project. All fields are read-only.

Screen Elements

Activities that cannot be Leveled field

The list of activities that the application cannot level.

Activities delayed by Leveling table

The ID and name of activities that have been delayed. Also shows the project ID and name of the project to which the activity belongs.

Project ID field

The unique identifying code for the project associated with the activity.

Project Name field

The name of the project associated with the activity.

Activity ID field

The unique identifier of the activity.

In order to identify and track activities, P6 assigns each activity a unique Activity ID that is the result of joining the Activity ID Prefix with the Activity ID Suffix and then adding an Increment value.

For example, a prefix of PROJ-A# combined with a suffix of 2500 and an Increment of 5 will yield the following activity IDs: PROJ-A#2500, PROJ-A#2505, etc.

Activity Name field

The name of the activity.

The activity name does not have to be unique.

Activities indirectly delayed by Leveling field

The activities indirectly delayed by leveling.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, click the Actions menu and select Run Leveler... (Shift+F9).
  4. In the Level Resources dialog box, click the Options tab.
  5. On the Options tab, select the Display leveling log upon completion and click Level.
  6. In the Leveling Report Log, expand the Leveling Results section.

Related Topics

About Resource Leveling

Leveling Project Resources



Last Published Thursday, April 3, 2025