Check Summary Section of the Schedule Check Report Dialog Box

Overview

Use this section to view a summary of project health based on the checks in the report.

Screen Elements

Check field

The type of check that was run for the schedule check report.

Examples of check types include Logic, Hard Constraints, and Negative Float.

Description field

The brief summary of the check.

Target field

The user-defined goal for each check.

You select this value using the Target selector in the Check Schedule dialog box.

Actual field

The percentage of the items found that match the check divided by the total number of items checked.

The Actual field for the BEI check displays a ratio. The cell is green if you hit your target, red if the target was missed.

Found field

The number of items found that match the check criteria.

Total field

The total number of items that were checked when the report ran.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. Click the Actions menu and select Check Schedule, then select View Report.

Related Topics

About Scheduling Projects



Last Published Thursday, April 3, 2025