Selecting an Activity for Review
Select an activity for review to enable the project manager or assigned status reviewers to approve the activity when updated by a team member before the status updates are applied to the project.
To select an activity for review:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Select an activity.
- Select the Review Required option.
Note: If the Review Required option is not displayed, click Customize View and select the Columns tab, then select Review Required from the General category.
- Save your changes.
Tip:
- Team member status reviews must be enabled in Project Preferences.
- If the Review Required option is not selected, status updates made by team members are approved automatically. View updates for each activity assigned to a team member in the Update History detail window.
Related Topics
About P6 Team Member Status Updates
Configuring P6 Team Member Status Update Reviews
Working with P6 Team Member Status Updates
Assigning a Status Reviewer to a WBS
Reviewing Team Member Status Updates
Viewing Team Member Status Updates History
Configuring P6 Team Member Status Update Reviews
Last Published Thursday, April 3, 2025