Selecting an Activity for Review

Select an activity for review to enable the project manager or assigned status reviewers to approve the activity when updated by a team member before the status updates are applied to the project.

To select an activity for review:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Select the Review Required option.

      Note: If the Review Required option is not displayed, click Customize View and select the Columns tab, then select Review Required from the General category.

    3. Save your changes.

Tip: