Creating Activity Relationships

You can create activity relationships in the Gantt chart to show interdependencies between activities.

To create an activity relationship:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Gantt View.
    2. Click Gantt Settings and select to show relationships.
    3. Hover either to the left or right of a bar.
    4. Drag the circle to the left or right end of a bar representing the activity you want to link.

      Note: Where you drag the relationship on each bar determines the type of relationship.

    5. Click Save.

Tip:

Related Topics

About Relationships

Configuring Activity Relationships

Assigning Predecessor Relationships

Configuring Predecessor Relationships

Assigning Successor Relationships

Configuring Successor Relationships

About Relationships



Last Published Thursday, April 3, 2025