Statistics Section of the Schedule Project Log Dialog Box of the Activities Page
Overview
Use this section to view activity statistics of the selected project. All fields are read-only.
Screen Elements
Number of Activities field
The number of activities associated with the selected project.
Number of Not Started Activities field
The number of activities that have not been started.
Number of In Progress Activities field
The number of activities that have been started but not completed.
Number of Completed Activities field
The number of activities that have been completed.
Number of Relationships field
The number of relationships within the activities.
Number of Activities with constraints field
The number of activities that have constraints.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, and click Schedule... (F9).
- In the Schedule dialog box:
- Configure the options and select the Display scheduling log upon completion option.
- Click Schedule Now.