Assigning Yourself to an Activity
Assign your resource to an activity so that you can add the activity to a timesheet.
- Select Timesheets
- Select ActionsÂ
, Assign Activity. - In the Assign Activities box:
- Select the project you want to assign yourself to.
A project-level setting determines whether a project is listed so you can assign yourself to its activities. If you need to assign yourself to a project that is not listed, contact your project manager or P6 administrator.
- Select one or more activities.
Note You can search for an activity either in all fields of the activity, or by restricting your search to the Activity ID, Activity Name, WBS, or Activity Status fields.
- Select Assign & Add to assign your resource to the activities and add the activities to your timesheet, or Assign to assign your resource to the activities without adding them to your timesheet.
- Select the project you want to assign yourself to.
Step me through...
Adding Activities to a Timesheet
Removing Activities from a Timesheet
Recording Actual Work Time on a Timesheet
Reporting a Completed Assignment
Editing Other Resource's Timesheets
Adding or Viewing Timesheet Notes
Saving or Printing a Timesheet