Create a baseline

  1. Open the projects for which you want to create a baseline.
  2. Choose Project, Maintain Baselines, then, if more than one project is open, select the projects for which you want to create a baseline.

    If you want to copy the current project as a new baseline or assign other projects as a baseline to the current project, you can select multiple projects.
  3. Click Add.
  4. Choose to save a copy of the current project as a new baseline or convert other projects into baselines of the current project, then click OK.

    If you choose to convert other projects, select the projects in the Select Project dialog box, then click the Select button.

Tip

Before converting a project to a baseline, if you still want to have access to the original project, you should make a copy of it. Once you convert a project to a baseline, it is no longer available in the project hierarchy. You can restore a baseline, making it available again as a separate project in the project hierarchy. You can also update a baseline with new/modified data from the current project.

Note

Related Topics

Update a baseline

Modify a baseline manually