Activities tab - Update Baseline dialog box

All Activities: Choose to update data for all activities or activities that meet a filter's criteria. If you select All Activities, updating the baseline will overwrite the entire baseline.

Show activities that match

All selected filters: When more than one filter is selected, choose to indicate that activities must meet all selection criteria in each filter.

Any selected filter: When more than one filter is selected, choose to indicate that activities must meet only one selection criteria in each filter.

Filter: Lists filter names according to filter category. Mark or clear the appropriate checkbox to apply or remove a filter. To search for a filter, start to type the name of the filter into the search box to limit the list.

Add new activities and activity data (except actuals): Mark to add new project activities and activity data (except actual units and costs) to the baseline. If you apply a filter, the module will add only new activities that meet the selected filter's criteria.

Delete from baseline any activities no longer in the current project: Mark to delete activities from the baseline that have been removed from the current project. If you apply a filter, this option is not available.

Update existing activities already in the baseline: Mark to update activities in the baseline with activity data that has been modified or added in the current project. If you select this option, click Update Options to select the types of activity and resource/role assignment data to update.