Baselines to Import dialog box

Use the Baselines to Import dialog box to specify which baselines to import when importing a project from a Primavera XML file. If any of the baselines included in the file were assigned as the project, primary, secondary, or tertiary baseline at the time the file was exported, you can also import baseline assignments.

Baseline Name: The project baselines that are available in the import file.

Exists: A read-only checkbox which shows whether the baseline already exists in the database. This checkbox will only show that a baseline exists in the database if you chose the Update Existing Project option in the Import Action field.

Baseline Type: A read-only field which shows the type of the baseline.

Import: Mark this checkbox to select a baseline to be imported.