Choose a calendar for relationship lag

  1. Choose Tools, Schedule.
  2. Click Options.
  3. On the General tab, select a calendar in the Calendar for Scheduling Relationship Lag field.

    Note:

    • Lag entered in a unit other than hours is converted to hours based on the predecessor activity's calendar.