Enter activity constraints

  1. Choose Project, Activities, then select the activity whose constraint you want to define.
  2. Display Activity Details, then click the Status tab.
  3. In the Primary field, select a constraint type.
  4. Click in the Date field, then select the date to which the constraint applies.
  5. In the Secondary field, select a constraint type (if necessary).
  6. Click in the Date field, then select the date to which the constraint applies.

    Note:

    • The Secondary constraint list is filtered based on the value you select in the Primary constraint field.
    • You cannot apply constraints to Level of Effort or WBS Summary activity types.