Recalculate resource and role assignment costs

  1. Choose Tools, Recalculate Assignment Costs to recalculate prices for all resources and roles on the project.
  2. Mark the Synchronize Overtime Factor while recalculating cost checkbox to synchronize the overtime factor defined for each resource when recalculating costs.
  3. Click Recalculate.

    Note:

    • Choosing this command recalculates activity costs in all open projects.
    • When connected to a P6 Professional database: Recalculate Assignment Costs is disabled if you do not have the View Resource and Role Costs/Financials global privilege.

When connected to a P6 EPPM database: Recalculate Assignment Costs is disabled if you do not have the appropriate global privilege as defined in P6.