Specify leveling priorities

  1. Choose Tools, Level Resources.
  2. In the Leveling Priorities area, click Add.
  3. Select a new leveling priority.

    A priority within the table takes precedence over any priorities below it.
  4. Specify a sort order.
  5. Click Level.

    Note:

    • To remove a priority from the list, select the priority, then click Remove.
    • To edit a priority, click the field name, then select a new field name and/or double-click the Sort Order column and select Ascending or Descending.
    • If multiple projects are open when you level resources, you must select which project's settings to use when leveling.