Adding Resources

Perform these steps to add resources to the resource pool. Resources include the personnel and equipment that perform work on activities across all projects. Resources are generally reused between activities and/or projects. Resources can be distinguished as either labor, material, or nonlabor. Labor and nonlabor resources are always time-based, and material resources, such as consumable items, use a unit of measure you can specify.

To add a resource:

  1. On the  Navigation Menu, expand  Resources and click Administration.
  2. On the Resources page, click Resources.
  3. On the Resources tab:
    1. Click  Add  and select Sibling Resource or Child Resource.
    2. In the Resource ID field, type an ID for the new resource.
  4. In the General detail window:
    1. Type a Resource Name for the resource.
    2. Select the Active option if the resource is available.
    3. Enter any other information in the appropriate fields.
  5. In the Units and Prices detail window:
    1. Click  Add.
    2. Configure the Effective Date, Max Units/Time, and Standard Rate.
    3. Enter any other information in the appropriate fields.
  6. Click Save.

Tip

  • If you intend to use reporting software, avoid using commas when creating data other than Project names. The way that data is passed to some reporting software can cause a comma to be interpreted as a delimiter between data items.
  • You can also importing resource data from a Microsoft Excel (.xlsx) spreadsheet.

Related Topics

Defining Resources and Roles

About Roles

Creating Roles

Assigning a Resource to a Role

Assigning a Role Team to a Role

About Role Teams

Creating Role Teams

Assigning a Role to a Role Team

About Resources

Assigning a Role to a Resource

Assigning a Resource Team to a Resource

Configuring Resource Settings

Assigning Calendars to Resources

Configuring Timesheet Reporting for Resources

Assigning Resource Codes

Assigning Resource Rates

Assigning Role Codes

Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

About Resource Teams

Creating Resource Teams

Assigning a Resource to a Resource Team



Last Published Wednesday, April 1, 2026