Configuring the Standard Work Week for Resource Calendars

Configure the standard work week for the calendar to set the work and nonwork days and hours for a standard work week.

To configure the standard work week:

  1. On the  Navigation Menu, expand  Administration and click Enterprise Data.
  2. On the Enterprise Data page, expand Resources and click Resource Calendars.
  3. On the Resource Calendars page:
    1. Click on the calendar you want to modify.
    2. Click the Standard Work Week tab.
  4. On the Standard Work Week tab:
    • Type the number of hours for each work day in the total hours field.
    • Or click and drag on the chart to create work periods for each work day.
  5. Click Save.

Tip

  • You can create multiple work periods for each day.
  • You can delete a work period by moving your mouse over the work period and clicking .""

Related Topics

Configuring Resource Calendars

Assigning a Base Calendar to a Resource Calendar

Assigning a Resource to a Resource Calendar

Setting Work Hours Per Time Period for a Resource Calendar

Modifying Calendar Days

Changing the Calendar Type



Last Published Wednesday, April 1, 2026