Setting the Resources Detailed Assignments Gantt Chart Timescale

Set the timescale interval of the Gantt chart and apply shading for non-work time.

Note If you only want to change the timescale, right-click the date bar in the Gantt chart and choose another timescale.

To set the timescale interval and apply shading for non-work time:

  1. On the  Navigation Menu, expand  Resources and click Assignments.
  2. On the Assignments page, click  Customize View.
  3. In the Customize View dialog box:
    1. Click Gantt.
    2. On the Gantt tab:
      • Click the Timescale list and select the timescale for the Gantt chart.
      • Select Non-work time shading to apply shading to non-work time represented in the Gantt.
    3. Click Apply.

Tip

If you select the Week/Day timescale, the following fields are not applicable: Period Actual Units, Period At Completion Units, Period Actual Cost, Period Actual Completion Cost.

Related Topics

Working with Resource Assignments in the Gantt Chart

Viewing Resource Assignments in a Gantt Chart

Configuring the Resources Assignments Gantt Chart Bars