Configuring Activity Code Values

Configure activity code values to reflect changing variations within the larger scope of the activity code.

To configure activity code values:

  1. On the  Navigation Menu, expand  Administration and click Enterprise Data.
  2. On the Enterprise Data page, expand Activities, then:
    • Click Activity Codes - EPS, expand an EPS node, then expand a code.
    • Click Activity Codes - Global, then expand a code.
    • Click Activity Codes - Project, expand a Project, then expand a code.
  3. Select an activity code value.
    1. In the Name field, double-click and type a name for the code value.
    2. In the Description field, double-click and type a brief narrative about the code value.
    3. In the Color field, double-click and select a color.

      Note In the Gantt chart and the Activity Calendar, activity status shown by activity code will display the color you apply to the activity code value.

  4. Click Save.

Tip

  • Activity code values at the same level are siblings. Subordinate activity code values are children.
  • You can also configure activity code values from the Codes detail window on the Activities page.
  • If you are working on the Activity Codes - Project page and the project you need is not visible, click Open Project. In the Open Projects dialog box, select a project from the Available Projects list, click "" to move the project to the Selected Projects list, and click OK.

Related Topics

About Activity Codes

Working with Activity Codes

Creating Activity Codes

Creating Activity Code Values

Selecting Items from a List of Available Items

Activity Codes - EPS Page

Activity Codes - Global Page

Activity Codes - Project Page