Adding Risk Response Plans
Projects > Risks > Project Risks > Managing Project Risks > Risk Response Plans > About Risk Response Plans
Add one or more response plans to a risk to plan alternative activities that might reduce the probability of a risk occurring, or to reduce the impact of the risk.
- On the
Navigation Menu, expand
Projects and click Risks. - On the Risks page, click a risk, and then click the Response Plans detail window.
- On the Response Plans detail window:
- Click
Add
and select Response Plan. - In the ID field, type a response plan ID.
- In the Name field, type a name for the new response plan.
- In the Response Type field, select a response type from the list.
- Click
- On the Risks page, click Save.
Note After you decide which response plan you are implementing, select the Active option next to the appropriate response plan.
Related Topics
Working with Risk Response Plans
Developing a Risk Response Plan
Adding Risk Response Plan Action Items
Assigning Activities to Risk Response Plan Action Items
Response Plans Detail Window of the Risks Page
Last Published Wednesday, April 1, 2026