Recalculating Assignment Costs

Recalculate assignment costs to update price per time values on activities. This ensures that project costs reflect any updates.

To recalculate assignment costs:

  1. On the  Navigation Menu, expand  Projects and click Activities.
  2. On the Activities page:
    1. Select an activity.
    2. Click Actions  and select Recalculate Assignment Costs.
    3. In the Recalculate Assignment Costs dialog box:
    4. (Optional) Select the Synchronize overtime factor while recalculating costs option to synchronize the overtime factor defined for each resource when recalculating costs.
    5. Click Recalculate.

Tip

  • When activity dates change, run Recalculate Assignment Costs to update resource costs based on the new dates.
  • These services are removed from the database based on the ASAP Cleanup Rate your P6 administrator specifies on the Configurations tab in Primavera P6 Administrator. Once the time is met all ASAP jobs that have a status other than running or delegated will be removed from the table automatically. Running and delegated jobs will be removed if they are older than the cleanup rate or if they are older than one day, whichever is greater.

Related Topics

About Activities

Working with Activities

Creating Activities

Copying and Pasting Activities

Renumbering Activities

Configuring General Activity Information

Assigning Locations to Activities

About Activity Types

About WBS Summary Activities

About Suspending and Resuming Activities

Dissolving Activities

About the Activity Table and Grid View

About Activity Networks



Last Published Wednesday, April 1, 2026