Schedule Check Report Dialog Box
Overview
Use this dialog box to configure the schedule check and to view potential issues in a schedule.
Screen Elements
- Check Schedule Settings Tab of the Check Schedule Dialog Box
- Report Tab of the Check Schedule Dialog Box
Getting Here
- On the
Navigation Menu, expand
Projects and click Activities.- Click the Actions
menu and select Check Schedule, then select Run Check Schedule.
- Click the Actions
Related Topics