Summary Columns of the EPS Table
Contains Summary Data option
Determines whether the project has been summarized. If the checkbox is marked, the project has been summarized.
Enable Summarization option
Determines whether a project will be summarized. If you select this option, the fields on the Summarization page are enabled. If this option is cleared, the project will not be summarized.
Last Summarized Date field
The date the project was last summarized. This is useful for assessing whether summary data for the project is current.
This field is blank for projects that have not been summarized.
Summarize Resources/Roles by WBS option
Determines whether resource and role summaries should be created at WBS level for the project. If this option is selected, then P6 will create summary data for resources and roles to the level determined by Summarize to WBS level.
Summarize to WBS Level list
Determines the depth of the WBS hierarchy for which summary data will be calculated and stored in the database. Level 1 is the project level, therefore if you select to summarize to WBS level 3, summary data will be calculated at the project level and for all first- and second-level WBS elements of the project. If you want to be able to drill down to lower levels of the WBS hierarchy when viewing or reporting on summarized data, change this setting to a higher number.