Selecting an Activity for Review

Select an activity for review to enable the project manager or assigned status reviewers to approve the activity when updated by a team member before the status updates are applied to the project.

To select an activity for review:

  1. On the  Navigation Menu, expand  Projects and click Activities.
  2. On the Activities page:
    1. Select an activity.
    2. Select the Review Required option.

      Note If the Review Required option is not displayed, click "" Customize View and select the Columns tab, then select Review Required from the General category.

    3. Save your changes.

Tip

  • Team member status reviews must be enabled in Project Preferences.
  • If the Review Required option is not selected, status updates made by team members are approved automatically. View updates for each activity assigned to a team member in the Update History detail window.

Related Topics

About P6 Team Member Status Updates

Configuring P6 Team Member Status Update Reviews

Working with P6 Team Member Status Updates

Assigning a Status Reviewer to a WBS

Reviewing Team Member Status Updates

Viewing Team Member Status Updates History

Configuring P6 Team Member Status Update Reviews



Last Published Wednesday, April 1, 2026