Resources Tab of the Level Resources Dialog Box of the Activities Page

Overview

Use this tab to specify which resources to level.

Screen Elements

All resources / Selected resources option

Determines whether all resources or only the resources you select are leveled.

Available

The list of resources available to level.

 Search

Enables you to perform a search based on the value you enter in the search bar.

Selected

The list of resources you selected from the available resources.

Getting Here

  1. On the  Navigation Menu, expand  Projects and click Activities.
  2. Click the Actionsmenu and select Leveler.
  3. In the Level Resources dialog box, click the Prioritization tab.