Completing Activities

Mark an activity complete when you have finished your work for the activity.

To mark an activity complete:

  1. Select an activity.
  2. In the activity pane, select  Mark Activity Complete (Ctrl+Alt+C).
  3. On the Status tab of the progress panel:
    1. Update the status fields.
    2. Update the Finished date if the finish date is not the scheduled Finished by date.

      Note You cannot set the Finished date to a date past the current date.

  4. Select Save.

Tip

  • Once you complete an activity, you can return the activity to an active state by selecting ""Mark Activity In-Progress.
  • If your activity entry is a milestone, select "" Mark Activity Complete (Ctrl+Alt+C) and update the Started date for a start milestone, or the Finished date for a finish milestone.
  • If the Update actual units when activities or assignments that were never started are marked complete in My Activities setting is selected in the General section of Application Settings and the activity you mark complete has never been updated, marking the activity complete will update the actual units for the activity to match the planned units.

Step me through...

Viewing Activities

Starting Activities

Changing Completed Activities to In Progress

Updating Activities

Updating Activities for Other Resources

Sending Email About an Activity

Starring Activities

Learn more about...

Working with Activities



Last Published Tuesday, March 31, 2026