Cost % of Budget (%)
Cost % of Budget threshold value is expressed as a percentage. An issue is generated if the ratio of the activity's actual cost to its budgeted cost (actual cost / budgeted cost * 100) falls beyond the threshold values.
Actual cost is the same as Total Actual Cost, and original cost is the same as Budget at Completion ( BAC).
The Cost % of Budget will reach 100 percent when the actual cost reaches the budgeted cost. The Cost % of Budget may be greater than 100 percent.