Project Earned Value Breakdown Section

Purpose
Use the Select a View list to determine whether this cost information displays as a bar chart or table. Regardless of the view chosen, the data is the same.
The bar chart breaks down data by the Project Manager project code and shows bars for:
- Actual Total Cost
- Earned Value (Cost)
- Planned Value (Cost)
- Estimate to Complete (Cost)
The x-axis shows Cost. The y-axis shows the Project Manager project code. Hover over a bar to see specific information.
The table breaks data down by Project Manager and shows columns for:
- Project Manager
- Actual Total Cost
- Earned Value (Cost)
- Planned Value (Cost)
- Estimate to Complete (Cost)
Location
- On the Home page, click Dashboards.
- Under Primavera, select Project Earned Value.
- On the Project Earned Value dashboard, click the Overview page.
- On the Overview page, expand the Project Earned Value Breakdown section.
Subject Area
Activity
Last Published Monday, January 5, 2026