Milestone Trend Analysis Section

Milestone Trend Analysis Section

Purpose

Use the trend analysis graph to help forecast milestone finish dates based on past data and analyses. The x-axis shows the reporting date. The y-axis shows the milestone finish date.

Location

  1. On the Home page, click Dashboards.
  2. Under Primavera, select More.
  3. On the More dashboard, click the d3 page.
  4. On the d3 page, expand the Milestone Trend Analysis section.

Subject Area

Activity