1.1.1 Pre-Feature Activation Overview

The pre-activation procedures shown in the following table may be executed outside a maintenance window if desired. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 1-1 Pre-Feature Activation Overview

Procedure Elapsed Time (Hours:Minutes) Activity Feature Activation Preparation Impact
This Step Cum.
System Topology Check 0:20 0:20
  1. Verify Network Element Configuration data.
  2. Verify System Group Configuration data.
  3. Analyze and plan DA-MP restart sequence.
None
Perform Health Check 0:05 0:25
  1. Verify DSR release.
  2. Verify server status.
  3. Log all current alarms.
None