Enabling a Resource Scheduler Schedule
Enable a Resource Scheduler schedule to manage resources.
- On the Schedules list page, find the Resource Scheduler schedule that you want to work with. If you need help finding the list page or the schedule, see Listing Resource Scheduler Schedules.
- From the Actions menu for the schedule, select Enable.
- When prompted, confirm the enabling.
When you enable the schedule, the Disable schedule option appears in the schedule's details page. The schedule's status become Enabled and its icon turns green. Use the oci resource-scheduler schedule activate command and required parameters to enable a Resource Scheduler schedule.
oci resource-scheduler schedule activate --schedule-id schedule_ocid [OPTIONS]
For a complete list of parameters and values for CLI commands, see the CLI Command Reference.
Run the ActivateSchedule operation to enable a Resource Scheduler schedule.