Defaults

1. Enter the Critical Work Center Code to be displayed or blank for all Work Centers.

Specify a code that indicates whether the work center is critical or not critical when the system calculates capacity. Values are:

Blank: All Work Centers.

N: Not a critical work center.

1: A critical work center in calculating RRP only.

2: A critical work center in calculating RCCP and CRP.

3: A critical work center in calculating RRP, RCCP, and CRP. The system also displays Type 3 work centers when you select type 1 or type 2 in this field.

4: Not a capacity work center. The system does not include this work center in capacity planning.

Note: The data selection is a system feature that processes certain groups of information with the RRP, RCCP, and CRP programs.
2. Enter the Capacity Mode:

Specify a code indicating which planning is being used. Values are:

1: Resource Requirements Planning.

2: Rough Cut Capacity Planning.

3: Capacity Requirements Planning.

3. Enter the default Unit of Measure.

Enter a value from UDC 00/UM (Unit of Measure) that identifies the unit of measurement for an amount or quantity.

For example, it can represent a barrel, box, cubic meter, liter, hour, and so on.