Process

Although processing options are set up during implementation, you can change processing options each time you run a program.

1. Beginning Status for History

Specify the beginning status in the range of work order statuses that the system displays.

2. Ending Status for History

Specify the ending status in the range of work order statuses that the system displays.

3. Number of Days of History to Display

Specify the range of work order creation dates to display.

The system uses this option to calculate the value in the Creation Date From field.

4. Work Order Type

Enter a value from UDC 00/TY (Work Order/ECO Type) that indicates the type of work orders to display.

5. Actual Finish Date From

Specify the From repair date for the range of work order repair dates.

6. Actual Finish Date Through

Specify the To repair date for the range of work order repair dates.