R3352 - Period Summary Report

You can specify the type of planning by selecting the appropriate report version. CAM uses the Capacity Requirements Planning version.

The system draws information for this report from these tables:

  • Capacity Load Table (F3313).

  • Capacity Pegging (F3312).

  • Work Center Master File (F30006).

When you set processing options for this report, consider that the system uses the Period From and the Period To dates that you enter:

  • If you enter dates in both fields, the system prints the summary within that period.

  • If you enter a date in the Period To field only, the system prints the summary beginning with the current period.

    If you do not select a Period From date, the system prints the past due orders before the current date.

  • If you enter a date in the Period From field only, the system prints all items from that date onward.

  • If more than one order for an item is scheduled at the work center for the same period, the system prints the item number once for each order in the report.