Revising Resource Units for a Work Center

You can revise resource units for a work center to correct over-capacity and under-capacity conditions. Use the Craft Resource Units form to make short-term revisions to the work center that is responsible for the maintenance tasks. For example, you can:

  • Indicate additional resources for a particular workday.

  • Revise the efficiency of the work center.

In addition, you can add or subtract workdays to the workday calendar. For example, you might want to add a Saturday to the workweek to compensate for an over-capacity condition.

Note: When you need to make permanent or long-term resource revisions to a work center, use the Work Center Master Revision form.