Default

Use this processing option to set the number of periods.

1. Number of Periods Prior to Current

Specify the number of periods prior to the current period the system uses to calculate completion metrics. For example, if you enter a "1" in this processing option the system will calculate completion metrics for the period just prior to the current period. If the current period is this week, one period prior is last week. If you leave this option blank, the system uses one period prior to the current period.