Defaults
Use these processing options to specify default values on the Work With Assignments form.
- 1. Schedule Period
Specify the default value for the schedule period. Values are:
1: Current Period (default)
2: Next Period
3: Following Period
- 2. Crew,3. Supervisor,4. Craft, and 5. Resource Type
Specify the default value for the crew, supervisor, craft, and resource type.
- 6. Load Profile Method
Specify how the work will be distributed across the duration of an assignment when a resource is assigned. For example, when you are using the flat load profile, the load is evenly distributed for the assignment across the duration. The current default value is:
1: Flat Load Profile