Forms Used to Assign Resources to Tasks

Form Name

FormID

Navigation

Usage

Work with Resource Assignments

W48331E

Daily Resource Assignment (G13RA10), Resource Assignment

The Work with Resource Assignments form supports these functions:

  • Assign resources to tasks.

  • Delete resource assignments from a task.

  • Equally distribute the hours required to complete the task between all assigned resources.

  • Report changes in availability for a selected resource.

Assignment Summary Review

W48331C

On the Work with Resource Assignments form, click the Summary Review link.

Change the date in the Scheduled Start Date field, and click Find.

Review summarized assignment information about the selected resource.

Adjust assignment information based on the revised scheduled start date.

Assignment Detail Review

W48331D

On the Work With Resource Assignments form, select Detail Review from the Form menu.

Review detailed resource assignment information such as the tasks to which the resource is assigned, the hours required for completion, and the percentage of the resource's capacity assigned to a task.