Process

1. Schedule Period

Specify whether to set default values for schedule period. Values are:

1: Current Period (default)

2: Next Period

3: Following Period

Set the default Forecast Type processing option based on the 34/DF UDC.

Set the default Supply & Demand Inclusion Rules processing option based on the 40/RV UDC. Use this processing option to specify the supply/demand inclusion rule that the system uses to determine what work orders or labor detail steps are active.

2. Forecast Type

Use this processing option to specify the forecast type to be used when creating PM projections. Enter a value from UDC 34/DF (Forecast Type).

3. Supply/Demand Inclusion Rule

Use this processing option to specify the supply/demand inclusion rule that the system uses to determine what work orders / labor detail steps are active. For schedules at the work order level, the system determines if the schedule is included by using the rule in this processing option, the work order document type (DCTO), and the work order status (SRST). For schedules at the labor detail level, the system determines if the schedule is included by using the rule in this processing option, the work order document type, and the operation status (OPST).

If the Operation Status field is blank, the system uses the work order status. Enter a value from UDC 40/RV (Inclusion Version). If you leave this processing option blank, the system calculates availability by using all assignments that have been identified for inclusion.