Understanding Schedule Metrics

The schedule metrics table contains all of the crew and craft availability and schedule compliance metric information that is supported throughout the crew scheduling process. The schedule compliance metric measures the performance of the crew in the process of creating a schedule of work and then completing that work. The following information is maintained by crew and craft for a schedule period:

  • Schedule Hours

  • Completed Schedule Hours

  • Completed Hours

  • Available Hours

  • Load Percent

The Crew Manage Schedule program creates a schedule for the crew in the next period and allows you to view current, following, and future scheduled work. After you review and update the schedule, you can use the Save Metrics option to save the schedule and update the scheduled hours for the crew and craft in the Schedule Metrics table (F48315).

The Schedule Completion Metrics report (R48327) is run after orders on the schedule are completed. The report updates the Completed Scheduled Hours and Completed Hours fields in the F48315 table. This report is typically run one to two weeks after the work has been completed to capture the completion metrics for the crew and craft.

The Schedule Metrics program provides an aggregate view of the metric information. The two key scheduling metrics that the report calculates are:

  • Schedule Compliance - Scheduled Completed / Total Scheduled.

  • Percent Scheduled - Scheduled Completed / Total Work Completed.