Changing the Build Status

Access the Work with Package Build Definition form.

  1. Find the package for which you want to reset the status.

    Below the package name, select the server or servers and client workstation for which you want to build the package.

  2. From the Row menu, select Advanced.

  3. On the Advanced Revisions form, click Reset to change the status of the package build from Build Started to Build Definition Complete.

  4. Click OK.

  5. If desired, select the package name and select Submit Build from the Row menu.

  6. The program asks whether you want to delete the current build or to continue without deleting it; select one.