The Normal Development Process

These lists provide an overview of how you should perform the normal development cycle.

In the DV900 path code, complete these tasks:

  • Make modifications.

  • Test the modifications.

  • Transfer the objects to PY900.

In the PY900 path code, complete these tasks:

  • Build the package.

  • Deploy the server objects to the PY900 path code on the enterprise server, and then test the objects.

  • Test the modifications.

  • Schedule the package.

  • Transfer the objects to PD900.

In the PD900 path code, complete these tasks:

  • Build the package.

  • Schedule the package.

  • Deploy the server objects to the PD900 path code on the enterprise server, and then test the objects.