The Normal Development Process
These lists provide an overview of how you should perform the normal development cycle.
In the DV900 path code, complete these tasks:
Make modifications.
Test the modifications.
Transfer the objects to PY900.
In the PY900 path code, complete these tasks:
Build the package.
Deploy the server objects to the PY900 path code on the enterprise server, and then test the objects.
Test the modifications.
Schedule the package.
Transfer the objects to PD900.
In the PD900 path code, complete these tasks:
Build the package.
Schedule the package.
Deploy the server objects to the PD900 path code on the enterprise server, and then test the objects.