Advancing Projects

Access Object Management Workbench - Web.

  1. In the Project grid, click the project you want to advance.

  2. Click the Change Project Status icon located in the Advance Project column. You can also click the Row button, and then click Advance Project.

  3. On the Confirm Project Status Change form, enter the new project status in the >>> field, or use the Visual Assist button to find a status.

    Your choices are limited, based on the current status of the project and on your company's specific procedures, which are defined in the JD Edwards EnterpriseOne OMW Configuration application.

  4. Click OK.

    Use the Web OMW logging system to view any errors that occurred during the status change. If you cannot advance the project, verify the following:

    • All of the objects in the project are checked in, including objects in projects that inherit a token.