Forms Used for Entering Indirect Costs, Bill of Material Information, and Actual Costs
Form Name |
Form ID |
Navigation |
Usage |
---|---|---|---|
Work with Actual Cost Process |
W76H6001A |
Actual Cost (G76H31), Actual Cost Process Header. |
View and select existing records. |
Actual Cost Process |
W76H6001B |
Click Add on the Work with Actual Cost Process form. |
Add indirect cost, bill of material, and actual cost information. |
Work With Item Actual Cost File |
W76H6105A |
On Actual Cost Process, select Actual Cost from the Form menu. Select Actual Cost Simulation from the Row menu to run cost simulation. Select Actual Cost Generation to run cost generation in either proof or final mode. |
Run the cost simulation and generation to enter actual costs. |
Manufactured Items |
W76H6008A |
On Actual Cost Process, select Actual BOM from the Form menu. Select Actual BOM Gen. from the Form menu |
Generate an actual bill of material. |
Bill of Material |
W76H6008B |
Select Bill of Material from the Row menu on the Manufactured Items form. |
Inquire on the actual bill of material that you generated. |
Work With Item Cost Component WF |
W76H6002F |
On Actual Cost Process, select Indirect Cost from the Form menu. |
Select costs to update. |
Cost Analyzer Balances Selection (Release 9.2 Update) |
W76H6002B/R76H6002 |
Select Balances Selection from the Form menu on the Work With Item Cost Component WF form. |
Select the records from the F1602 table to update. Update records interactively or by batch mode. |
Rates Selection |
W76H6002C |
Select Rates Selection from the Form menu on the Work With Item Cost Component WF form. |
Select F1642 and F16421 records to update. Update records interactively or by batch mode. |